Home Projects

Muskrat Falls to Churchill Falls Transmission Line

See All Projects
Project Details

Completion Date: June 2016

Location: Churchill Falls

Services Rendered by

Valard Construction

Learn More

Two Parallel 315kV Alternating Current (AC) Transmission Lines.

The project was 490.4 km in length from Muskrat Falls Hydroelectric Generating Facility to the electricity infrastructure at Churchill Falls.

  • 1,271 towers installed – including 1,001 guyed structures & 270 self-supporting structures.
  • 3,211,022 bolts were used to install 11,896 metric tons of steel.
  • Crews installed 2,081 foundations and 4,364 anchors.
  • The total length of conductor installed was 6,296.7 km.
  • There were 889 staff working on the project for a total of 1,155,452 labor hours.

 

 

 

 

Click for more details

Related Projects

Demobilization was completed December 22, 2018
SID TO OPP Flowline Repair (Spy Island Drilling site to Oliktok Point Plant)

Repair a corroded subsea Arctic oil flowline running 18,459 ft from an offshore man-made island to shore facilities on the Arctic coast.

View Project
helicopter flying over trees
March 29, 2019
Fort McMurray West 500-kV AC Transmission Project

Largest EPC project ever awarded in North America The West Fort McMurray (WFMAC) 500 kV Transmission Line Project includes over 310 miles of high voltage...

View Project
December 2018
Fisk 345 kV Transmission Lines

The project involved new 345 kV transmission lines just outside downtown Chicago.

View Project
Back to Top