Valard Completes Historic Transmission Line in Record Time

Published on Back To Index

The Fort McMurray West 500-kV Transmission Project (WFMAC) hit its “construction complete” milestone 91 days ahead of schedule. Now that it has been energized, it has already begun its 35-year operating period.

After four-and-a-half years, the Valard Group of Companies transferred the project to ATCO’s operation and maintenance team. In December 2014, Alberta Powerline as part of a Valard/ATCO partnership, won the bid for the 500-plus km transmission line, which included two substations, from Edmonton to Fort McMurray, Alberta, Canada.

Read More at T&D World

Recommended Posts

Back to index
In the News
New York Power Authority Awards $93 Million On-Call Construction Contracts to Advance Digital Communications Infrastructure

August 8, 2019 NYPA Trustees Approve Contract to Bolster Reliability and Efficiency of the New York State Energy Grid...

Learn More
In the News
VRCA showcases Silver Award of Excellence winners

August 8, 2019 VANCOUVER – The Vancouver Regional Construction Association (VRCA) is celebrating and showcasing its members’ best work...

Learn More
In the News
ENR Mountain States Announces 2019 Best Projects Winners

July 31, 2019 ENR Mountain States is pleased to announce the winners of the 2019 Best Projects competition across a seven-state region that includes...

Learn More
Back to Top