Home Projects

Entergy Lake Charles 230/500kV Transmission Project

See All Projects
Project Details

Completion Date: February 2018

Location: Lake Charles, LA

Client: Entergy

Services Rendered by

15 miles of 230kV, 6.8 miles of 500kV

Dashiell, a Quanta Services company, was awarded the EPC contract by Entergy in early 2015 for the Lake Charles Transmission Project. Dashiell was supported by Irby Construction Company, another Quanta Services company, on this project. Dashiell’s main focus was engineering and Irby’s main focus was the rebuilding and constructing of power lines.

 

 

 

 

Related Projects

Demobilization was completed December 22, 2018
SID TO OPP Flowline Repair (Spy Island Drilling site to Oliktok Point Plant)

Repair a corroded subsea Arctic oil flowline running 18,459 ft from an offshore man-made island to shore facilities on the Arctic coast.

View Project
helicopter flying over trees
March 29, 2019
Fort McMurray West 500-kV AC Transmission Project

Largest EPC project ever awarded in North America The West Fort McMurray (WFMAC) 500 kV Transmission Line Project includes over 310 miles of high voltage...

View Project
December 2018
Fisk 345 kV Transmission Lines

The project involved new 345 kV transmission lines just outside downtown Chicago.

View Project
Back to Top