Project Details

Completion Date: Demobilization was completed December 22, 2018

Location: Oliktok Point and Spy Island located on the North Slope of Alaska along the Beaufort Sea.

Services Rendered by

Repair a corroded subsea Arctic oil flowline running 18,459 ft from an offshore man-made island to shore facilities on the Arctic coast.

This process entailed fabricating and pushing/pulling a new 10.75” flowline into the corroded 14” pipeline to serve as a replacement flowline, while minimizing production shutdown time.

 

 

Related Projects

September 2019
Mountain Valley Pipeline – Spread E

The project is a total of 27 miles of 42 inch diameter pipe.

View Project
November 2018
Mountaineer Express – Spreads 5 & 6

Spread 5 - 20 Miles of 36”, Spread 6 - 30 Miles of 36”

View Project
Workers performing construction on a pipeline
August 2017
Maurepas Pipeline, LLC, Subsidiary of Semgroup

QPSE provided engineering, procurement, environmental permitting and construction services for three pipelines: a 34-mile, 6-inch olefins pipeline; a 36-mile, 12-inch vacuum gas oil (VGO) pipeline;...